This is general guidance based on standard permitted development rights in England. Rules differ for listed buildings, conservation areas, and properties with Article 4 directions. Always confirm with your local planning authority before starting work.

Usually Permitted DevelopmentNorth Kesteven (East Midlands)

Do I Need Planning Permission for an EV Charging Point in North Kesteven?

Installing an electric vehicle charging point on your property. Wall-mounted and post-mounted chargers have specific permitted development rights under Part 2 of the GPDO.

Planning in North Kesteven

97%

of planning applications granted

96%

decided within the statutory or agreed time

71%

of householder applications decided within 8 weeks

In the year to December 2025, North Kesteven decided 637 planning applications. 307 of these were householder projects such as extensions, loft conversions and outbuildings, of which 99% were granted.

Planning statistics: MHCLG planning application statistics, the year to December 2025. Conservation area and Article 4 data: planning.data.gov.uk, © Historic England / Crown copyright. Open Government Licence v3.0.

Important: Additional Restrictions May Apply in North Kesteven

North Kesteven has 38 conservation areas. These include Aswarby, Bassingham, Beckingham, Billinghay, Blankney, Bloxholm. If your property is in a conservation area, some or all permitted development rights may be restricted. For example, you may need planning permission for changes that would normally be permitted, including alterations to the roof, cladding, or extensions visible from a public highway.

Check with North Kesteven planning department before starting work to confirm whether your property is affected by any special designations.

Permitted Development Rules for an EV Charging Point

Generally permitted under Part 2, Class D of the GPDO. One charging point is permitted per property. Wall-mounted units must not face a highway. The unit must not exceed 0.2 cubic metres in volume.

Conditions

  • 1One charging point per property under PD
  • 2Wall-mounted units must not be on a wall facing a highway
  • 3Must not exceed 0.2 cubic metres in volume
  • 4Must not be within 2m of a highway (for post-mounted units in designated areas)
  • 5Must not be on a listed building or within the curtilage of a listed building (in designated areas)

Size and Dimension Limits

  • Maximum volume: 0.2 cubic metres
  • One unit per property under PD

When Permitted Development Does Not Apply

  • Not PD on listed buildings or within the curtilage of a listed building in designated areas
  • Post-mounted units in designated areas must not be within 2m of a highway
  • A second charger requires planning permission
  • Electrical installation must be carried out by a qualified electrician

What About Building Regulations?

Building regulations approval is likely required

The electrical installation must comply with Building Regulations Part P. The work should be carried out by a registered electrician (NICEIC, NAPIT, or equivalent) who can self-certify the installation. The charger must comply with BS 7671 (IET Wiring Regulations) and have appropriate circuit protection.

Building regulations are separate from planning permission. Even if your project is permitted development, you may still need building regulations approval. Contact North Kesteven building control or use an approved inspector.

How to Apply in North Kesteven

If you need planning permission for your ev charging point, you can apply through North Kesteven's planning department or via the national Planning Portal.

Timeline:8 weeks for householder planning applications if PP is needed.
Cost:£258
Visit North Kesteven Planning

If your project is permitted development and you want written confirmation, you can apply for a Lawful Development Certificate (LDC) from North Kesteven. This provides proof that your project does not need planning permission, which can be helpful when selling your property.

What Happens If I Build Without Permission?

Very low risk. EV chargers are small and unobtrusive. Enforcement is only likely if the unit is on a listed building without consent or is a second unit installed without permission.

Frequently Asked Questions

Do I need planning permission for an ev charging point in North Kesteven?
Generally permitted under Part 2, Class D of the GPDO. One charging point is permitted per property. Wall-mounted units must not face a highway. The unit must not exceed 0.2 cubic metres in volume. Note: North Kesteven has 38 conservation areas (including Aswarby, Bassingham, Beckingham) where permitted development rights may be restricted. Check with North Kesteven planning department.
Does an ev charging point in North Kesteven need building regulations?
Yes. The electrical installation must comply with Building Regulations Part P. The work should be carried out by a registered electrician (NICEIC, NAPIT, or equivalent) who can self-certify the installation. The charger must comply with BS 7671 (IET Wiring Regulations) and have appropriate circuit protection. Contact North Kesteven building control or an approved inspector for details.
How do I apply for planning permission in North Kesteven?
You can apply for planning permission through North Kesteven's planning department or via the national Planning Portal. £258. 8 weeks for householder planning applications if PP is needed..
How long does planning permission take in North Kesteven?
Most planning applications should be decided within 8 weeks (13 weeks for major projects). In the year to December 2025, North Kesteven decided 96% of applications within the statutory or agreed time, and 71% of householder applications within 8 weeks.
What percentage of planning applications does North Kesteven approve?
North Kesteven granted 97% of the 637 planning applications it decided in the year to December 2025. For householder applications such as extensions and outbuildings, the approval rate was 99%.

Find an EV Charger Installer in North Kesteven

Browse local ev charger installers on Tradesfolk. Read reviews, compare quotes, and hire with confidence. 100% free for homeowners, always.

EV Charging Point rules in nearby council areas

Other projects in North Kesteven